Interior · Drywall

Drywall Calculator

Sheets, screws, tape and mud from your room sizes, and what it costs to have it hung and finished in your area.

Costs checked: November 2026Code basis: 2021 IRC R702.3Sources

1 Rooms
ft
ft
ft
21 ft² each
15 ft² each
Units
2 Board
%
10% typical; 15% with many openings
3 Location and labor

Region factor ×1.00: U.S. national average. How it’s derived

Who does the work
Sheets
17
4×8 incl. 10%
Board area
477ft²
walls 333 + ceiling 144
Screws
512
28/wall sheet, 35/ceiling
Joint compound
4.8gal
2 × 4.5 gal buckets

Drywall list

Drywall list
ItemQtyNotes
Drywall sheets 4×817
Drywall screws 1¼ in. (½ in. board)512IRC R702.3.5 spacing: 16 in. walls, 12 in. ceilings
Joint tape204 ft1 × 500 ft rolls
All-purpose joint compound2 buckets (4.5 gal)
Outside corner bead, 8 ftcount corners
Low
$716
Typical
$1,070
$2.25 per ft² of board
High
$1,430
Region
×1.00
U.S. national average
Cost breakdown
ItemQuantityLowTypicalHigh
Hang, tape and two coats477 sq ft$716$1,070$1,430
Split
Materials$215$322$429
Labor, equipment & overhead$501$751$1,000
Total installed$716$1,070$1,430
Angi: labor is roughly 70% of a drywall job. Finish level is the big price lever; prices are per square foot of board hung.

Costs checked: November 2026. Ranges are published national figures (see Sources below) times the regional factor. They exclude permits, sales tax and unusual site work. Get at least three local quotes.

How the drywall calculator works

It starts from the rooms, not a total area, because doors and windows don’t need board and ceilings take a different fastener spacing. Walls are perimeter × height minus 21 ft² per door and 15 ft² per window (a standard 3 × 7 ft door and 3 × 5 ft window); the ceiling is length × width. Sheets come from the total board area plus waste. Screws are counted from the code spacing for each surface, and tape from the joints each sheet creates.

Board = walls + ceiling Sheets = ceil(board × (1 + waste) ÷ sheet area) Screws = sheets × (framing members crossed) × (screws per member: 16 in. walls, 12 in. ceilings) Tape = sheets × (sheet width + length) (each sheet shares half its edges) Compound ≈ board ÷ 100 gallons (taping + two coats)

Worked example: a 12 × 12 ft bedroom, 8 ft walls

  • Walls 48 × 8 = 384 ft², minus a door (21) and two windows (30) = 333 ft². Ceiling 144 ft². Board 477 ft².
  • Sheets: 477 × 1.10 ÷ 32 = 16.4 → 17 sheets of 4 × 8.
  • Screws: about 12 wall sheets × 28 + 5 ceiling sheets × 35 ≈ 512.
  • Tape: 17 × 12 = 204 ft (one 500 ft roll); compound about 4.8 gallons (2 buckets).
  • Installed, hang, tape and two coats: 477 × $1.50 / $2.25 / $3.00 = $716 / $1,073 / $1,431, about 70% of it labor.

Hanging tips that save mud

  • Hang ceilings first, then walls, with the top wall sheet tight to the ceiling.
  • Run sheets horizontally on walls and stagger the butt joints; never let four corners meet at one point.
  • Don’t break a sheet’s joint at the edge of a door or window opening: run the sheet past and cut out the opening, so the joint lands mid-span and is less likely to crack.
  • Set screws just below the surface without tearing the paper. Torn paper means a screw that doesn’t hold.

What changes the price

  • Finish level: hang-only is a fraction of a finished job; a level-5 skim coat for gloss paint or raking light costs most.
  • Ceiling height and access: rooms over 9 ft need scaffolding or lifts; stairwells cost more.
  • Board type: moisture-resistant, mold-resistant, fire-rated Type X and soundproofing boards cost more than standard ½ in.
  • Small jobs: repairs and single rooms often carry a minimum charge.

Insulating the walls first? The insulation calculator works out the batts. Painting afterwards? The paint calculator uses the same room inputs.

Finishing levels in plain English

Level 3 suits heavy textures; level 4 is the usual finish for flat or eggshell paint; level 5 adds a skim coat over everything for gloss paint or walls hit by raking light. Each level adds material and labor, which is why the finish is the biggest lever on drywall cost.

Questions people ask

How many sheets of drywall do I need for a 12×12 room?
With 8 ft walls, one door and two windows, the walls are 333 ft² and the ceiling 144 ft², 477 ft² in all. With 10% waste that is 17 sheets of 4 × 8 ft, or 11 sheets of 4 × 12 ft.
How many screws per sheet of drywall?
IRC Table R702.3.5 sets screw spacing at 16 in. on walls and 12 in. on ceilings for framing 16 or 24 in. on center. On a 4 × 8 sheet hung across studs at 16 in., that is 7 studs × 4 screws = 28 on a wall and 7 × 5 = 35 on a ceiling.
How much joint compound do I need?
A common estimating rule is about 1 gallon of ready-mixed compound per 100 ft² of board for taping and two finish coats, so roughly 5 gallons for a 12 × 12 room. Level-5 skim coats and heavy textures use much more.
How much does drywall installation cost?
Angi’s 2026 data: hanging only about $0.80–$1 per ft² of board; hang, tape and two coats $1.50–$3; a level-5 skim-coat finish $2–$3.50. HomeAdvisor’s overall range is $1.50–$3.50 per ft². Angi puts labor at roughly 70% of the job.
Should I use 4×8 or 4×12 sheets?
Longer sheets mean fewer butt joints, which are the hardest to finish flat. On walls 12 ft or longer, 4 × 12 sheets hung horizontally save tape and mud. They are heavy and awkward, though, so 4 × 8 is easier for one person and for ceilings.

Sources

Costs checked: November 2026. Each range is the published figure from the source named next to it; where we did arithmetic on a published figure the page says so. Regional factors: how they’re derived.

  1. How Much Does Drywall Installation Cost? — Angi, checked Nov 2026.
  2. How Much Does Drywall Installation Cost? — HomeAdvisor, checked Nov 2026.
  3. 2021 International Residential Code (IRC) — International Code Council, checked Nov 2026.
  4. Cost vs. Value 2025: national and regional data — Remodeling magazine / Zonda (JLC), checked Nov 2026. Job costs for 13 projects in 9 Census divisions; used for regional factors and benchmark projects.

Related calculators

All interior tools →